Gostyn II

Fabricación de las torres.

Hub height

120 meters

Wind turbine

AW125/3000

Number of towers

10 towers

Year of Construction

2015

Tower Type

Full-Concrete Tower / Tower Design: NORDEX

Client

ACCIONA WINDPOWER S.A.

Local Partnership

In 2015, Nordex (though its Polish subsidiary Acciona WindPower S.A) hired WINDTECHNIC to supply 10 concrete towers designed and developed by the turbine manufacturer for its AW125/3000 wind turbine. The 120-meter-high structures were produced in collaboration with Pekabex* for the Gostyn II wind farm located in Szurkowo.

The 220 concrete keystones were manufactured and transported by the Pekabex-Windtechnic consortium at Pekabex’s facilities in Poznań in less than 9 weeks during the second quarter of 2015.

*Pekabex is a local Polish company dedicated to the precast sector with over 50 years of experience and 5 factories distributed throughout Poland and Germany.