Diseño y certificación de torre.
Creación de manuales y procedimientos de fabricación y montaje.
Supervisión durante fabricación y montaje de las torres.
110 meters
Full-Concrete Tower / Tower Design: WINDTECHNIC
SERVENG GROUP
In 2013, WINDTECHNIC designed and certified a 110-meter-high tower for a 1.6 MW-capacity turbine manufactured by GE.
The prototype was installed in the wind farm developed by the Serveng Group in the region of Rio Grande do Norte, Brazil.
For the prototype, WINDTECHNIC defined all the manufacturing and assembly procedures as well as the quality control system.
In addition, several WINDTECHNIC experts traveled to Brazil to supervise the execution of the tower according to the established procedures.
Our team of experts in engineering and construction of concrete towers is always ready to offer customized and sustainable solutions adapted to your needs.